Second Severn Crossing - Maintenance Works
Client: Severn Bridge PLC
Main Contractor: Laing 'O Rourke
Completion Date:
June 2004
Location:
Severn Estuary - UK
Key Statistics:
Duration: 15 months
Value: £4.7M
Project Overview:
This contract primarily concerned
refurbishment works to the Second Severn Crossing bridge. The
strengthening of existing mono rail running the full length of the
crossing
involved replacement of some 2000 mid-span brackets and cleats. In addition the existing main span
gantry and RAT (rapid access train) were removed by barge, refurbished
at the works and
re-fitted.
|